Start here, lesson 3
Critical path and float without the jargon
The critical path is commonly described as the sequence of activities whose delay would delay completion. That is useful, and a live project is messier than the definition.
- Jurisdiction
- General; float ownership is contract specific
- Law and editions as at
- 3 August 2026
- Last reviewed
- 3 August 2026
- Editorial status
- Editorial draft, not yet independently reviewed
The path the software calculates
A scheduling tool calculates criticality from the logic, durations, calendars and constraints it has been given. Change any of those and the calculated path changes. That is not a flaw, but it does mean the red bars are an output of the model rather than a fact about the project.
The path the site was actually on
Logic changes. Resources move. Access constraints appear. Contractors resequence. Near-critical work becomes critical. A programme can contain constraints or settings that make a path look critical while the site was working somewhere else entirely.
The analyst therefore tests the calculated path against the factual one: what were site managers prioritising and why, which missing design or access or material constrained the next operation, what do the quantities and resources show, do the minutes and look-aheads identify the same priority, and did the apparent constraint really govern or was it an artefact of the model.
Float
Float is the amount of time an activity can slip before it affects something that matters. Total float measures slack against the completion date; free float measures slack before the next activity is affected. Both are properties of the model, so both change every time the model changes.
Technical guidance The Society of Construction Law Protocol’s starting position is that, unless the contract says otherwise, float is not owned exclusively by either party and is broadly available to the project, with entitlement questions biting when employer delay pushes completion beyond the contractual date. That is guidance, and amendments frequently take a different position.
In practice the float question is a drafting question. Clauses that allocate float to the employer, or that require the contractor to absorb delay while float remains, are common. Read the contract before reading anything else about float, including this page.
Pacing
Pacing is the deliberate slowing of work in response to a delay elsewhere, on the reasoning that there is no point racing to a gate that is already shut. It is legitimate in principle and frequently indistinguishable, in a bare programme, from contractor delay. What separates them is contemporaneous evidence of the decision, which is another reason narratives and minutes matter.
Where the record comes in
Every mechanism on this page turns on evidence: what happened, what was known and when. A record built as the job happens is worth more than any argument assembled afterwards. Construction Metric keeps that record automatically, from the messages, photographs and voice notes a site team already sends.
Built by AI Metric
The analysis on this site is only as fast as the evidence behind it. AI Metric builds bespoke systems for consultancies, contractors and claims teams: document and correspondence triage, event registers assembled from the project record, programme and cost reconciliation, and drafting support that always cites the document it came from. Built for review by your own experts, never to replace their judgement.
Do not overread this page
Float ownership and the treatment of pacing vary by contract and jurisdiction. Nothing here overrides an express clause.
General explanation of how contract mechanisms, analysis methods and legal principles generally work. It is not legal or contractual advice, not an opinion on any project, and no standard-form contract wording is reproduced anywhere on this site. Standard forms are routinely amended, so every default described here, including every time period, can be different on your project. Your executed contract, as amended, and the governing law and forum always control. Deadlines may already be running: if an event has occurred, preserve your position and take qualified advice.