Critical path: calculated and factual

A calculated critical path is an output of a model. A factual controlling path is a finding about the project. Delay analysis lives in the gap between them.

Jurisdiction
General method guidance
Law and editions as at
3 August 2026
Last reviewed
3 August 2026
Editorial status
Editorial draft, not yet independently reviewed

What makes a path critical in the model

Logic, durations, calendars, constraints and progress. Change any one and criticality moves. Constraints are the usual culprit: a mandatory start, a deadline constraint or a stale actual date can hold a path critical long after the work stopped controlling anything.

Settings that quietly change the answer

  • Retained logic against progress override, which changes how out-of-sequence progress is calculated.
  • Calendars applied inconsistently across activities, so a delay is absorbed by a weekend that the site actually worked.
  • Open ends, where activities have no successor and therefore never drive anything.
  • Long lags substituting for real activities, hiding what the project was actually waiting for.
  • Level of detail so coarse that the controlling work is buried inside a summary bar.

Testing the model against the project

  1. What were site managers prioritising, and what do the minutes say they were waiting for?
  2. Which missing design, access, approval or material constrained the next operation?
  3. What do installed quantities and resource allocations show about where the work actually was?
  4. Do the look-aheads issued at the time identify the same priority as the model?
  5. Did the apparent constraint genuinely govern, or is it an artefact of a setting?

Where the two disagree, the disagreement is the finding. An analysis that reports a calculated path without testing it against the record has described its own model rather than the project.

Near-critical work

Paths with small float become critical the moment anything slips, and on a compressed project several paths sit within days of each other. Reporting only the single longest path in that situation overstates certainty. Identify the near-critical paths in each period and say how close they were.

Where the record comes in

Every mechanism on this page turns on evidence: what happened, what was known and when. A record built as the job happens is worth more than any argument assembled afterwards. Construction Metric keeps that record automatically, from the messages, photographs and voice notes a site team already sends.

Built by AI Metric

The analysis on this site is only as fast as the evidence behind it. AI Metric builds bespoke systems for consultancies, contractors and claims teams: document and correspondence triage, event registers assembled from the project record, programme and cost reconciliation, and drafting support that always cites the document it came from. Built for review by your own experts, never to replace their judgement.

Do not overread this page

Identifying the controlling path shows what took the time. It does not identify who was responsible for it, and it does not decide entitlement.

General explanation of how contract mechanisms, analysis methods and legal principles generally work. It is not legal or contractual advice, not an opinion on any project, and no standard-form contract wording is reproduced anywhere on this site. Standard forms are routinely amended, so every default described here, including every time period, can be different on your project. Your executed contract, as amended, and the governing law and forum always control. Deadlines may already be running: if an event has occurred, preserve your position and take qualified advice.