Skip to content
Quantum Delay Metric

Delay · disruption · quantum

When a project runs late, the programme is only the beginning.

A construction project can miss its completion date for a dozen reasons at once. Drawings arrive late. Access is partial. A subcontractor underperforms. A variation changes the sequence. Crews stay longer and install less each hour. The dispute begins with one question, who caused the delay, and it cannot be answered in one step.

This publication follows the chain from contract to conclusion. It does not treat a colourful schedule as a verdict, it does not use professional guidance as though it were law, and it does not pretend an answer from London transfers unchanged to Sydney, California, Riyadh or Dubai.

Every legal proposition on this site carries its source class

Primary lawJudgmentContract textTechnical guidanceCommentary

A judgment, a contract clause and a consultant’s article are not the same currency. Law and editions checked as at 3 August 2026.

The claim chain

Break one link and an impressive model proves nothing

Exact contract, governing law and forum, event and notice, factual causation, critical-path or productivity effect, legally recoverable loss, reliable evidence. Every guide on this site sits somewhere on that chain, and every case study shows what happens when a link is missing.

  1. 1

    Contract

    Which clause allocates the event, and what does it require?

  2. 2

    Notice

    What started the clock, to whom must notice go, and what happens if it is late?

  3. 3

    Fact

    What changed on site, when, where and because of whom or what?

  4. 4

    Time

    Did the event affect the critical or contractually relevant path?

  5. 5

    Money

    What additional cost or lost productivity did that event cause?

  6. 6

    Law and forum

    Which rules govern interpretation, evidence and remedy?

Current legal watch

The UAE Civil Transactions Law changed on 1 June 2026

Federal Decree-Law No. 25 of 2025 took effect on 1 June 2026 and repealed Federal Law No. 5 of 1985, subject to transitional questions that need advice. Any resource still describing the 1985 code as the current mainland civil code needs review, and that includes templates, precedent bundles and training material.

Built by AI Metric

Bespoke AI and automation for delay and quantum teams

The analysis on this site is only as fast as the evidence behind it. AI Metric builds bespoke systems for consultancies, contractors and claims teams: document and correspondence triage, event registers assembled from the project record, programme and cost reconciliation, and drafting support that always cites the document it came from. Built for review by your own experts, never to replace their judgement.