Records
Programme updates and narratives
A monthly update that changes dates without explaining logic is not a contemporaneous analysis. It is a moving picture with its labels removed.
- Jurisdiction
- General practice
- Law and editions as at
- 3 August 2026
- Last reviewed
- 3 August 2026
- Editorial status
- Editorial draft, not yet independently reviewed
Preserve with every update
- The native file, and a read-only snapshot in a format that cannot be edited later.
- The data date and the update period.
- Actual starts, actual finishes and remaining durations.
- Every logic, activity, calendar, constraint and coding change, with a reason.
- How out-of-sequence progress was treated.
- The longest path and the near-critical paths.
- A progress and critical-path narrative in words.
- Links to events, instructions and mitigation.
- Who prepared it, who checked it and who approved it.
Why the narrative is the valuable part
The numbers can be recalculated years later. The reasoning cannot. A narrative that says why the critical path moved, what the team was waiting for and what it did about it converts a schedule into evidence, and it takes twenty minutes a month.
Rejected programmes
If a programme is rejected, preserve the submission, the reasons and the resubmission. Rejection does not suspend planning, and the contract may attach consequences to acceptance or compliance that only make sense if the sequence of submissions is documented.
The test to apply
Could a competent analyst who has never seen the project reconstruct, from this month’s pack alone, what changed and why? If not, the pack is incomplete, and the gap will be argued about later by people who were not there.
Read next
Where the record comes in
Every mechanism on this page turns on evidence: what happened, what was known and when. A record built as the job happens is worth more than any argument assembled afterwards. Construction Metric keeps that record automatically, from the messages, photographs and voice notes a site team already sends.
Built by AI Metric
The analysis on this site is only as fast as the evidence behind it. AI Metric builds bespoke systems for consultancies, contractors and claims teams: document and correspondence triage, event registers assembled from the project record, programme and cost reconciliation, and drafting support that always cites the document it came from. Built for review by your own experts, never to replace their judgement.
Do not overread this page
Programme content, submission and acceptance requirements are contractual. This page describes good practice, not an obligation.
General explanation of how contract mechanisms, analysis methods and legal principles generally work. It is not legal or contractual advice, not an opinion on any project, and no standard-form contract wording is reproduced anywhere on this site. Standard forms are routinely amended, so every default described here, including every time period, can be different on your project. Your executed contract, as amended, and the governing law and forum always control. Deadlines may already be running: if an event has occurred, preserve your position and take qualified advice.
