Daily site records that prove facts

A daily record is evidence of fact. The moment it starts arguing, it stops being evidence and starts being a document the other side will enjoy reading aloud.

Jurisdiction
General practice
Law and editions as at
3 August 2026
Last reviewed
3 August 2026
Editorial status
Editorial draft, not yet independently reviewed

The eight things every entry should fix

  1. Time: start, finish, interruption and resumption, not just a date.
  2. Place: level, zone, grid, room. A building has hundreds of places and the claim will need the right one.
  3. People: crew identifier, trade, headcount, supervision.
  4. Work: the activity, and the installed quantity where there is one.
  5. Cause: what prevented or changed the work, described as observation rather than blame.
  6. Corroboration: who else saw it, which photographs, which request or instruction.
  7. Mitigation: what the crew did instead, and what it produced.
  8. Linkage: the event identifier, the programme activity, the cost code.

Photographs

A photograph with no location, date, author or direction is decoration. Capture metadata automatically wherever possible, keep the originals, and record what the photograph was taken to show. Chain of custody matters more than resolution.

Oral instructions

Record the exchange, mark it for formal confirmation, and send the confirmation. An oral instruction that was never confirmed is a dispute waiting to happen, and the note made that afternoon is usually the only surviving evidence that the conversation occurred.

What not to write

No conclusions about entitlement, no characterisation of another party’s conduct, no assessment of critical-path effect. Those are for later, by people with the whole picture. A diary that reaches them early is easy to discredit, and once one entry is discredited every other entry is read differently.

Where the record comes in

Every mechanism on this page turns on evidence: what happened, what was known and when. A record built as the job happens is worth more than any argument assembled afterwards. Construction Metric keeps that record automatically, from the messages, photographs and voice notes a site team already sends.

Built by AI Metric

The analysis on this site is only as fast as the evidence behind it. AI Metric builds bespoke systems for consultancies, contractors and claims teams: document and correspondence triage, event registers assembled from the project record, programme and cost reconciliation, and drafting support that always cites the document it came from. Built for review by your own experts, never to replace their judgement.

Do not overread this page

Keeping good daily records does not create an entitlement or satisfy a contractual notice requirement. Notices are a separate obligation with their own form and timing.

General explanation of how contract mechanisms, analysis methods and legal principles generally work. It is not legal or contractual advice, not an opinion on any project, and no standard-form contract wording is reproduced anywhere on this site. Standard forms are routinely amended, so every default described here, including every time period, can be different on your project. Your executed contract, as amended, and the governing law and forum always control. Deadlines may already be running: if an event has occurred, preserve your position and take qualified advice.